Midstate Barrier, Inc.
1 approval totalling $1,428,778 approved by the county.
Every figure below was read out of the wording of the matter the Board voted on; the exact wording is shown under each one. This page states what the Board approved and who voted for it, and nothing beyond that.
26-2915 $1,428,778
AWARD and AUTHORIZE the Public Works Director, or designee, to execute a construction contract with Midstate Barrier, Inc. in the amount of $1,428,778 for the Countywide Guardrail Upgrades Phase II, Countywide area. (33% Highway Safety Improvement Program State Funds, 67% Local Road Funds)
Where these figures come from
Counterparty: “contract with Midstate Barrier, Inc.”
Amount: “in the amount of $1,428,778”
Both spans are quoted from the title of matter 26-2915 as the county published it.
Approved on the consent calendar, on this roll call: Yes Candace Andersen, Diane Burgis, John Gioia, Ken Carlson, Shanelle Scales-Preston